D0 Data Reprocessing
D0 data is often reprocessed using the last version of the D0 Reconstruction Software in order to become available for analysis.
Reprocessing were done for the P14, P17 and for P20 versions of the D0 Reconstruction Software:
- P14: November 2003-January 2004
- P17: March-November 2005
- P20: February-June 2007
P17 Reprocessing
SPRACE has participated in the
P17 Reprocessing, together with other 7 farms in Canada, USA, and Europe.
1 Billion events were reprocessed using SAMGrid infrastructure in all farms. SPRACE started the reprocessing in August 2005, and it was able to reprocess 10 Million events.
P20 Reprocessing
SPRACE has participated in the
P20 Reprocessing, together with other 16 remote farms in Canada, USA, and Europe.
The OSG interoperability was used to allow SAMGrid jobs to be executed in OSG clusters, and 400 Million events were reprocessed in those OSG remote farms. SPRACE was able to reprocess 18.4 Million events.
An updated statistic for the P20 Reprocessing can be seen
here.
--
SergioNovaes - 18 Jan 2008